Federal Environmental Permit Reform – Streamlining Energy Projects

Federal Environmental Permit Reform – Streamlining Energy Projects

by Gavin L. Biebuyck, Principal, Air Quality Expert at Liberty Environmental

The U.S. Senate voted this month to pass an environmental permitting-reform bill (H.R. 2347), the “Bipartisan American Affordability and Jobs Act of 2026” (BAAJA). The bill is aimed at streamlining environmental review of large energy infrastructure projects like pipelines, power plants, and transmission lines. If the bill is passed and is ratified by the House, it will represent one of the largest changes to environmental permitting procedures in decades. It would overhaul the 1970 National Environmental Policy Act (NEPA) to exempt certain projects, set tighter deadlines for approvals, and limit the ability of the public to sue. It would also speed issuance of permits/approvals under the Clean Water Act (NPDES permits) and under the Endangered Species Act.

Increasing strain on the electric grid from new electric demand has led many States and the Federal government to focus on permitting reform to avoid years-long delays that have been experienced for energy projects. For example, regulatory challenges led to a 10-year delay in constructing a 300-mile gas pipeline through Virginia and West Virginia. Similarly, environmental impact challenges led to a 20-year delay in construction of a wind farm and transmission line in New Mexico. The bill would streamline both oil and gas projects but also clean energy projects like wind/solar, and associated transmission lines. For this reason, the bill has bipartisan support in Congress due to its benefits for both oil and gas and clean energy projects.

In addition, it would make it harder for a President to unilaterally block energy projects. Specifically, it would limit the ability of presidents to revoke already-issued federal permits, and would allow companies to sue federal agencies that hold up energy projects for an “unreasonable” length of time (e.g., 9 months, 1 year, to 2 years, depending on type of approval).

Notable elements of the bill include the following:

  • Exempting certain projects from NEPA review including expansion of existing pipelines or power lines along existing routes.
  • Tightening deadlines for federal agency review/issuance of approvals (e.g., 90 to 60 days, 150 to 100 days for endangered species certifications).
  • Defining “reasonable period of time” for permit/approval issuance (e.g., less than 9 months for wetland certifications).
  • Limiting judicial review by preventing Courts from halting projects if they find the environmental review inadequate. Agencies could be ordered to update their reviews while project construction continues.
  • Changing NPDES permit term from 5-years to 10-years.
  • Limiting State’s ability to object to gas pipelines under the Clean Water Act.
  • Streamlining timeline for new nuclear energy facility licensing.
  • New “Permitting Certainty” provisions prohibiting federal re-consideration of previously Approved projects:

“a Federal department or agency shall not take any new action that would revoke, rescind, withdraw,  terminate, suspend, vacate, remand, reopen, materially amend, or materially alter a Federal authorization or permit in effect on or after November 6, 23 2026”

  • Increasing funding for Brownfields projects (Section 1602 – Brownfields revitalization) by increasing loans/grants. Total annual grant amount increases from current $50 million to $60-80 million per year over the 2027-2031 period.
  • Providing “ratepayer protection” with regard to large new electric loads from data centers. Allowing States to identify data centers as new class of electric customer with different rates/fees.

This federal permit reform for energy projects comes on the heels of many States implementing “expedited permit review” programs.  These programs provide permit review timing certainty, typically with higher application fees, and in some cases using private contracted review firms (e.g., PA DEP’s “SPEED” permitting program).

The bill has the support of the majority of Republicans and the President as it certainly “cuts red tape” and will expedite permitting of oil and gas projects. Several Democrats also support the bill because they believe it will accelerate approval of new wind farm and solar energy projects as well as the interstate electric transmission lines necessary for wholesale green energy adoption. However, many environmental NGOs object to the bill’s limits on judicial review and public appeal opportunities.  In addition, the recent mid-term election results give the Democrats to re-craft the bill in 2027. But the public pressure for Congress to do something about skyrocketing electric bills and the impact of data centers has allowed passage through the Senate and now the House will consider the bill this December.

While these permit reform efforts are encouraging and can provide “permit certainty” for applicants, it is important to ensure that permit applications are complete in order to “start the clock” for the guaranteed permit review timetables. All of the expedited permit programs include provisions to “stop the clock” in the event applications are found to be missing information or are deemed to be technically deficient.

A link to the BAAJA bill is here:

https://www.congress.gov/bill/119th-congress/senate-bill/5653/text